- Methodology For Forming And Optimizing The Material Delivery Schedule In Construction
- UDC 69.05:658.512.6
doi: 10.33622/0869-7019.2026.02.23-27
Dmitry V. TOPCHIY, topchiydv@mgsu.ru
Ekaterina P. CHUPRAKOVA, chuprakovaep@mgsu.ru
National Research Moscow State University of Civil Engineering, Yaroslavskoe shosse, 26, Moscow 129337, Russian Federation
Abstract. This article examines a comprehensive methodology for developing an iterative schedule for the delivery of construction materials, integrated with the work production schedule. The aim of the research is to propose an algorithm that synchronizes supply logistics with the dynamics of construction processes and site constraints, thereby minimizing construction equipment downtime and optimizing the use of storage areas. The methodology is based on the sequential adjustment of the work schedule, taken from the construction project plan, considering the production capacity of key machinery, logistics chains, and the analysis of storage area load. The key result is an iterative model that ensures a balance between the requirements of the construction pace, logistical capabilities, and site resources. The method allows for a quantitative assessment of production efficiency through the reduction in the need for equipment, labor, and storage space. The conclusion highlights the necessity of applying digital modeling tools to implement the proposed methodology and for its further development.
Keywords: construction organization, construction site logistics, material delivery schedule, calendar planning, storage optimization, the iterative model - REFERENCES
1. Optimization of construction: stages and methods. Available at: https://academy.peri.ru/blog/optimizatsiya-stroitelstva (accessed 15.12.2025). (In Russ.).
2. Rozanceva N. V., Zolotarev V. V. Formation of an effective schedule of work during the construction of a monolithic reinforced concrete house. Vestnik MGSU, 2024, no. 19(10), pp. 1676-1686. (In Russ.). doi: 10.22227/1997-0935.2024.10.1676-1686
3. Bazanov V. E. On the norms of labor costs in the preparation of work schedules in modern conditions. Stroitel'noe proizvodstvo, 2019, no. 1, pp. 37-39. (In Russ.).
4. Kisel' T. N., Prohorova Yu. S., Chzhimin' C. Features of digitalization of enterprises of various types of activity. Vestnik MGSU, 2025, no. 20(11), pp. 1794-1805. (In Russ.). doi: 10.22227/1997-0935.2025.11.1794-1805
5. Aktual'nye voprosy stroitel'stva na Dal'nem Vostoke Rossii. Materialy nauch.-prakt. konf. [Current issues of construction in the Russian Far East. Proc. of the Scientific and Practical Conference (Khabarovsk, February 25, 2025)]. Khabarovsk, DVGUPS Publ., 2025. 180 p. (In Russ.).
6. Gurinovich V. Yu., Pozdnyakov D. A., Leonovich S. N. Optimization of production in conditions of production of a wide range of products. Vestnik MGSU, 2025, no. 20(3), pp. 419-428. (In Russ.). doi: 10.22227/1997-0935.2025.3.419-428
7. Borodkin K. Yu., Shilov D. V., Kabanov V. N. Optimization of labor costs in monolithic construction: an engineering approach to the calculation of temporary structures. Promyshlennoe i grazhdanskoe stroitel'stvo, 2025, no. 7, pp. 56-60. (In Russ.). doi: 10.33622/0869-7019.2025.07.56-60
8. Zolotozubov D. G., Kaloshina S. V., Sazonova S. A., Tat'yannikov D. A. Rational placement of warehouses on the construction site. Construction and Geotechnics, 2020, vol. 11, no. 3, pp. 117-126. (In Russ.). doi: 10.15593/2224-9826/2020.3.10
9. Kievskiy L. V. Calendar planning using S-functions. Promyshlennoe i grazhdanskoe stroitel'stvo, 2025, no. 12, pp. 4-10. (In Russ.). doi: 10.33622/0869-7019.2025.12.04-10
10. Kievskiy I. L., Zharov Ya. V., Musina S. K. et al. Development of digital competencies of engineering and technical staff in the development of organizational and technological documentation. Promyshlennoe i grazhdanskoe stroitel'stvo, 2024, no. 11, pp. 27-34. (In Russ.). doi: 10.33622/0869-7019.2024.11.27-34 - For citation: Topchiy D. V., Chuprakova E. P. Methodology for Forming and Optimizing the Material Delivery Schedule in Construction. Promyshlennoe i grazhdanskoe stroitel'stvo [Industrial and Civil Engineering], 2026, no. 2, рp. 23-27. (In Russ.). doi: 10.33622/0869-7019.2026.02.23-27
BACK